LNG plant self-use
Supports an approximately 3.7MW plant load with operating margin.
10MW-class LNG plant expansion
A containerized AM1200 solution designed to secure LNG plant power first, create a clear grid-export basis second, and retain standby capacity for continuous operation.
Conceptual public solution. Final configuration follows confirmed gas, load, grid and site data.
One platform. Three duties.
The design separates essential plant demand, potential export generation and operating reserve. This lets the project evaluate export capacity without weakening LNG plant reliability.
LNG plant self-use
Supports an approximately 3.7MW plant load with operating margin.
Grid export basis
Gross export capacity basis for grid or embedded-power evaluation.
Standby and maintenance
Reserve capacity is excluded from routine export-energy calculations.
Integrated route
CIMC coordinates the generator-side interfaces as one modular EPC and lifecycle system.
AM1200 reference 1.2MW per unit
Internal architecture 4 x 300kW generator modules
Indicative envelope 10.5m x 3.0m x 3.2m
Clear project boundary
The generator package can be standardized, but the final EPC boundary still depends on gas treatment, civil conditions, the PCC and local execution responsibilities.
Engineering flexibility
Both arrangements preserve modular grouping and maintenance access. The preferred option follows the final site redline, gas inlet, cable route, lifting plan and grid connection point.
Clear equipment sequence with straightforward access along a shared utility spine.
Reduced footprint with central access for utilities, transformers and maintenance.
Modular by design. The same building-block logic supports later capacity expansion without redesigning the entire plant concept.
Electrical architecture
The reference architecture groups four AM1200 units behind each step-up transformer package, then coordinates the plant feeder and external grid interface through the agreed control and protection philosophy.
Move from concept to engineering
Detailed pricing follows only after the technical boundary and operating model are confirmed.
Composition, delivery pressure, temperature, flow and operating envelope.
Current LNG process load, operating hours, critical-load profile and growth plan.
Target voltage, PCC location, export approval, offtake route and protection requirements.
Redline, access, gas inlet, cable route, fire spacing and maintenance clearances.
Tariff, gas cost, O&M assumptions and grid availability remain client-specific inputs. Commercial performance is evaluated after the technical boundary is confirmed.
Built to expand
Share the site data and CIMC will develop the equipment configuration, interface list, preliminary layout and delivery route for discussion.
Start project assessment